Key Concepts
Procurement basics appear on the PMP exam, and the project manager is almost always a critical stakeholder in procurement decisions, even when a separate team handles the mechanics. This task covers providing project-specific information, monitoring vendor performance for its impact on schedule and quality, and keeping procurement integrated with the rest of the project.
Managing procurement is a topic some project managers do not get exposed to much. Maybe your organization has a dedicated group that looks after this work. Perhaps all your projects to date have been internal or direct to a client, and nothing extra was needed.
Either way, procurement basics, including contract types and handling suppliers, are in the PMP exam, so we need to understand it. Also, even if you have a separate purchasing or procurement department, the project manager is often a critical stakeholder providing project-specific information and ensuring procurement issues do not negatively impact the project.
2.11.1 Define Resource Requirements and Needs
When planning a project, we analyze the scope to determine what will be required, either as part of a deliverable or something we will use along the way. Some elements we may already have on-hand, some things we can build ourselves. Everything else we have to outsource or buy, whether skills or goods, this is where procurement comes in.
Procurement Strategy
Procurement Strategy encompasses planning the procurement process. This includes
- Analyzing scope of requirements
- Performing make-or-buy analysis
- Making the make-or-buy decisions
- Creating a Procurement Management Plan
- Creating a Statement Of Work (SOW) for each procurement
Make or Buy?
When performing make-or-buy analysis, information is gathered about product requirements and then an evaluation is performed between purchase or internal manufacture of the product. Factors evaluated include:
- Impacts on time, cost, or quality? (E.G., Do we have time to make it, or should we just buy it?)
- Do we have the skills? (Can we make it? Would it be as good as a bought one?)
- Is there an ongoing need for these specific skill sets? (is it worth training or hiring for?)
- How steep is the learning curve?
- Are the required resources and skills available within the organization?
Procurement Management Plan
The Procurement Management Plan is a component of the project or program management plan. It describes how a project will acquire external goods and services. The plan defines:
- The timetable of key procurement activities
- Types of contracts to be used
- Process for obtaining and evaluating bids
- Procurement documents that will be used
- How multiple providers will be managed
- Any prequalified sellers
2.11.2 Communicate Resource Requirements
Communication
Once we know what we want to buy, we need to start communicating with prospective sellers.
Whenever dealing with people, especially external people, there is the potential for miscommunication. This could lead to a costly mistake when working in the field of procurement, so we should err on the side of over-communicating our objectives, the project needs, and success criteria.
Some tips for managing procurement communications include:
- Add vendors and suppliers to the Communications Management Plan and administer their details and communication needs like all the other project stakeholders
- Provide periodic progress reports of supplier activities
- Share notifications of potential supplier cost overruns, schedule delays or issues with relevant stakeholders
- Provide acknowledgments back to suppliers when they communicate to verify the message was received and ask for the same to confirm that communication is occurring
- Provide formal acceptance of supplier’s contracted deliverables.
Source Selection Criteria
The set of attributes desired by the buyer. The list of things a seller is required to meet or exceed to be selected for a contract.
The types of things typically asked for by a buyer as source selection criteria include:
- Overall or life-cycle cost – How much will it cost?
- Understanding of need – Demonstrate you know what we are asking for
- Technical capability – Can you do it?
- Delivery and life cycle approach – Tell us how you work
- Management and technical approach – Tell us how you operate
- Warranty – How long we want it guaranteed for
- Financial capacity – Tell us about your financials
- Production capacity and interest – Tell us about your capabilities
- Business size and type – Tell us about your org size and structure
- Past performance – What else have you done
- Customer references – Who can we go to for references?
- Intellectual property right policies – Our IP requirements
- Proprietary rights – Other rights and policies.
Qualified Vendors
Sometimes we might have a set of approved sellers to choose from known in advance. These are qualified vendors approved to deliver products or services based on the procurement requirements identified. The list of qualified vendors may come from historical information about different vendors, or if the requirement is new to the organization, market research can help identify qualified resources.
Qualified Vendors List
2.11.3 Manage Suppliers/Contracts
Contracts
Contracts are mutually binding agreements. They obligate the seller to provide the specified product or service and obligates the buyer to pay for it. Contracts are typically customized for each agreement and vary in type.
Components of Contracts
- Description of the work being done, its deliverables, and scope
- Delivery dates or other schedule information
- Identification of authority and decision making, where appropriate
- Responsibilities of both parties
- Management of technical and business aspects
- Price and payment terms
- Provisions for termination and dispute resolution
- Applicable guarantees and warranties
Common contract types include:
Fixed-price (FP) – a set fee that will be paid for defined work, regardless of the cost or effort to deliver. Suited for projects with high degrees of certainty about their scope and operating parameters.
- Pros – Provides maximum protection to the buyer
- Cons – Requires lengthy estimation and potential for padding by the seller.
Cost-reimbursable (CR) – A contract that involves paying the seller for the seller’s actual costs, plus a fee. This fee often represents the seller’s margin or profit. Suited for projects where the scope or parameters are uncertain. Requires the seller to have an accounting system that can track all costs by project.
- Pros – Can be structured to include incentives for meeting schedule, cost or technical performance targets.
- Cons – The buyer bears most of the cost risk because the total costs are unknown.
Time-and-material (T&M) – A hybrid between Fixed-price and Cost-reimbursable where the buyer pays on a per hours basis plus the cost of any materials. It is suited for projects where the level of effort cannot be determined upfront.
- Pros – Good for projects that are difficult to estimate
- Cons – They can lead to cost and schedule overruns over long periods since the seller’s profit is built into the hourly rate. So there is no incentive for them to finish early. To limit this, T&M contracts often come with a Not-to-exceed clause.
Different contract types favor the buyer or the seller in the ownership of financial risk. These are shown below.
In a Fixed-price (FP) contract, the Buyer risk of a cost overrun is low as the price has been agreed on ahead of time. Conversely, the seller risk is high. Time and Materials (T&M) contracts with a not-to-exceed clause are somewhere in the middle. While Cost-reimbursable (CR) contracts have a low risk for the seller and a high risk for the buyer.
Statement of Work (SOW)
A Statement Of Work (SOW) describes a chunk of work in sufficient detail to allow prospective sellers to determine if they can provide the products, services, or results asked for.
SOWs are created from the project scope baseline and are sent to potential vendors. SOWs should be clear and specific as possible to avoid ambiguity or confusion.
If vendors are interested in bidding on the work, they respond, and the buyer evaluates their response. SOWs form the basis of other procurement documents used during the procurement process.
Bid Documents
Bid documents are used to ask for proposals from sellers. Depending on the goods or services needed, the bid documents can include a Request For Information (RFI), Request For Quotation (RFQ), Request For Proposal (RFP), or other documents. Each is typically used when:
- Request for information (RFI) – when more information on the goods and services is needed from the sellers. Typically followed by an RFQ or RFP.
- Request for quotation (RFQ) – when more information is required on how vendors will satisfy the requirements and/or how much it will cost.
- Request for proposal (RFP) – when the solution is not easy to determine. This is the most formal of the RFx documents and has strict rules for content, timeline, and seller responses.
Bidder Conferences
In addition to sending out documents, organizations often hold meetings prior to submissions of a bid or proposal by the vendors. These meetings explain the requirements, terms and conditions, and answer vendor questions.
Bidder conferences aim to ensure all the vendors have a clear and common understanding of the technical and contractual requirements for the procurement. These bidder conferences might also be known as pre-bid conferences, pre-proposal conferences, vendor conferences, or contractor conferences.
2.11.4 Plan and Manage Procurement Strategy
Once an organization has evaluated the responses from sellers and selected a vendor, they then need to manage the procurement process to ensure they get what they asked for. Also, as the project progresses, they may need to handle additions, changes, and disputes.
In short, procurements need to be tracked and managed like a mini-project in their own right.
Control Procurements Process
The Control Procurements process is the act of managing procurement relationships, monitoring contract performance, making changes and corrections as appropriate, and finally closing out contracts.
Procurement activities are integrated into the overall project plan to ensure:
- The vendor’s work is sanctioned to begin at the appropriate time.
- Performance reporting to monitor vendor costs, schedule, and technical performance.
- Change control is in place to ensure that changes are managed and properly approved.
- Quality controls exist to ensure that the quality of the vendor’s product or service meets requirements.
- Monitor and control any project risks associated with vendors or their work to ensure that the risks are correctly managed.
Because agile approaches are frequently used when it is difficult to define requirements, this can lead to procurement and contract challenges. Without detailed, unchanging statements of work, many vendors are understandably reluctant to enter into fixed-price contracts. Some of the contract types that have been created to mitigate this risk include:
Incremental Delivery Contracts use small work packages to reduce the risk of under or over-estimating a large piece of work by breaking it down into smaller chunks. Single, large SOWs are split into smaller work packages, each with its own fixed price. As the work progresses, the vendor can re-estimate the remaining work packages based on new information.
Using incremental delivery contracts with fixed-price work packages allows the customer to reprioritize remaining work based on evolving priorities and costs. It also removes the need for vendors to build excess contingency funds into the project cost.
Due to the popularity and growth of agile approaches, the need and interest in conducting procurement aligned to agile projects have expanded. Organizations such as Lean and Agile Procurement (LAP) have sprung up to provide examples, case studies and training. Project managers tasked with procurement in these environments will likely find many valuable ideas.
2.11.5 Develop a Delivery Solution
Even when the contract is in place and the vendor/seller is providing goods or services, we still need to periodically check the quality and manage changes.
Changes to contracts are tracked and managed via a Contract Change Control System.
Contract Change Control System
The system and process used to collect, track, adjudicate and communicate changes to a contract. It might be part of the project’s integrated change control system or its own separate system. It specifies the process for handling contract changes and includes documentation, the dispute-resolution procedures, and approval levels needed to authorize the changes to contract details.
Standard contract change types include:
- Administrative changes – non-substantive changes of something minor. These are the most common type of changes. For example, “Payment terms have been changed from Net 90 days to Net 60 days.”
- Supplemental agreement – a new, additional agreement that may be related to the contract but is negotiated separately. For example, “Starting July 1st, 2 sacks of donkey pellets will be added to the weekly order for pig food.”
- Contract modification – a substantive change such as a new deadline or a change to the product requirements. For example, “Starting July 15th, all deliveries must be made by lunchtime (12:00 noon) to avoid a 10% angry pig holdback.”
- Constructive changes – any changes the buyer causes through action or inaction. For example, “Due to sleepy pigs in warm weather, delivery quantities will be reduced by 20% July – September.”
- Termination of contract – A contract may be terminated due to vendor default, issues, or at the customer’s request. Defaults include late deliveries, poor quality, or non-performance of project requirements. For example, “Due to a failure to deliver pig food when scheduled, the petting zoo is terminating the food contract and will be switching to a different supplier effective August 1st.”
Disputes and Legal Concepts
Of course, these changes are not always popular or thought of by the buyer or seller as fair, so disputes can occur. Legal action is also sometimes threatened or taken. The legal concepts project managers need to be aware of when dealing with procurement include:
- Warranty – A explicit or implied promise that goods or services will meet a pre-defined standard. The standard may cover reliability, safety, quality, fitness for use, etc.
- Waiver – The giving up of a contract right, even if it occurred inadvertently.
- Breach of contract – The failure to meet some or all of the requirements of a contract. It could result in damages paid to the wronged party, litigation, or other consequences.
- Cease and desist (C&D) letter – A letter sent to a person or business to stop (cease) the allegedly illegal activities and do not do them again (desist). C&D letters are often used as an indication of forthcoming legal action if it is disregarded.
Closing Procurements
The terms and conditions of a contract typically specify how contracts are closed out. These terms should also be in the procurement management plan. Usually, a written notice is provided to the seller when the agreement is complete. Procurements can be closed at any time throughout the project’s life, not only at the end.
The project manager should ensure that the seller provided all the required products or services and settle any remaining invoices and payments. Also, address any outstanding contracting issues.
Some organizations may conduct a procurement audit to identify successes and failures of the procurement process and evaluate the seller’s performance.
Deliverables and Tools
- Market Research
- Statement Of Work (SOW)
- Procurement Management Plan
- Source selection criteria
- Make or Buy Analysis
- Negotiations
- Prepare agreements
- Monitor work / deliverables
- Process change requests
Related Topics
- 1.9 Collaborate with stakeholders
- 2.4 Engage Stakeholders
- 2.5 Plan and manage budget and resources
- 2.6 Plan and manage schedule
- 2.7 Plan and manage quality of products/deliverables
- 2.8 Plan and manage scope
- 2.13 Determine appropriate project methodology and practices
- 2.14 Establish project governance structure
- 2.15 Manage project issues
- 3.3 Evaluate and address external business environment changes
FAQ
Why do project managers need to know procurement?
Procurement basics appear on the PMP exam, and the PM is almost always a critical stakeholder in procurement decisions.
What is the project manager’s role?
Provide project-specific information, monitor vendor performance for its impact on schedule and quality, and keep procurement activities integrated with the project.
What if the organization has a dedicated purchasing group?
The mechanics may be handled elsewhere, but the project manager remains a key stakeholder in procurement decisions.
Further Reading
- Website: Lean Agile Procurement
Quiz Summary
0 of 5 Questions completed
Questions:
Information
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading…
You must sign in or sign up to start the quiz.
You must first complete the following:
Results
Results
0 of 5 Questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 point(s), (0)
Earned Point(s): 0 of 0, (0)
0 Essay(s) Pending (Possible Point(s): 0)
Categories
- Not categorized 0%
- 2.11 Procurement 0%
-
-
Congratulations! You earned the Plan and Manage Procurement badge.(Must be logged in to be awarded badges)
See your achievements
| Pos. | Name | Entered on | Points | Result |
|---|---|---|---|---|
| Table is loading | ||||
| No data available | ||||
- Review
- Answered
- Correct
- Incorrect
Explore these topics via an interactive mind map. (Click the nodes to expand/collapse, drag to pan, scroll/pinch to zoom.)